Yet another update from Jennifer and Barry detailing their LV Home build:
We installed the tallest faux wall panels first onto the Simpson strong walls, then proceeded to install the panels on the back of the house where the large sliding doors/windows will be. After lifting the parapet panels onto the roof, Kevin measured the parapet height on each panel, nailed a 2x4 onto the panel, and we were able to hang the panel onto the side of the house while Kevin nailed each into place.
This is coming along quite nicely. We're definitely looking forward to seeing the final result.